For garbage and recycling, residents are only responsible for placing the carts at the end of the driveway. It is the contractor's responsibility to move the carts if needed. If the garbage or recycling does not get picked up, send an email.
Schedule
The second lift of pavement will be applied to the entire project at the same time in the fall after Phase 2 and 3 are complete. Once sod is placed, the contractor maintains the watering for 30 days from the date of placement.
September 19
Final pouring of curb and gutter.
Starting work on driveways resulting in driveway closures beginninh on Merrimac and Olive Lane. Look for a notice on the garage door for the times you are unable to park in your driveway. Expect some congestion on the roads during this time.
This schedule is subject to change due to weather and contractor's schedule. Drive slowly around equipment and in construction areas for your safety and that of the construction workers. Please make eye contact with construction workers while driving, and they will wave when safe to proceed.